Fuselage Construction of my Rans S6S Page 2 |
||
|
Final assembly & engine install
|
3/20/06 |
Completed installation of control stick assembly, or as far as I can go at this point. Began cutting and trimming interior plastic panels. |
4.25 hrs |
|
|
|||
|
3/21/06 |
Assembled and began install of seats. |
2.5 hrs |
|
|
|
|||
|
3/22/06 |
Finished installing seats. Began vertical stab construction. |
2.5 hrs |
|
|
3/23/06 |
Installed top stringer and finished vert stab. Constructed right horizontal stab. |
2.5 hrs |
|
|
3/24/06 |
Constructed left hor stab. Installed both elevators. Riveted and installed trim tab |
2.25 hrs |
|
|
|
|||
|
3-25-06 |
Assembled rudder, rudder cables and pulleys |
2.0 hrs |
|
| 3-26-06 | Assembled and installed elevator push pull tube | 2.0 hrs | |
|
|
|||
| 3-27-06 | Assembled and installed flap handle assembly | 1.5 hrs | |
|
7-30-06 |
Install aft baggage compartment internal parts. Still need to assemble and install door. |
2.0 hrs |
|
| 8-6-06 | Install frame and door for aft baggage. Removed tail group in prep for covering. Installed side formers. | 6.0 hrs | |
| 8-7-06 | Installed longeron fairings. Began prep for fuselage covering. | 2.5 hrs | |
| 8-13-06 | Removed interior panels and finished missing rivets. Prepared fuselage for fabric | 9.0 hrs | |
| 8-29-06 | Fabricated and installed bracket for elt after reviewing regs came up with what I feel is a good location with appropriate strength i.e. meets the 100 pound pull test. Fabricated and installed antenna mount plate for elt antenna. | 3.5 hrs | |
|
|
|||
|
|
|||